CHECK ON OPEN TRAVERSE
In open traverse, the measurements cannot
be checked directly. But some field measurements can be taken to check the
accuracy of the work. The methods are discussed below.
1. Taking
cut-off lines
 Cut-off lines are taken between some
intermediate stations of the open traverse. Suppose ABCDEF represents an open
traverse. Let AD and DG be the cut-off lines. The lengths and magnetic bearings
of the cut-off lines are measured accurately. After plotting the traverse, the
distances and bearings are noted from the map. These distances and bearings
should tally with the actual records from the field

2. Taking
an auxiliary point 
Suppose ABCDEF is an open traverse. A
permanent point P is selected on one side of it. The magnetic bearings of this
point are taken from the traverse stations A,B,C,D, etc. If the survey is
carried out accurately and so is the plotting, all the measured bearings of P
when plotted should meet at the point P. The permanent point P is known as the
‘auxiliary point’