LESSON NOTE ON CHECK ON OPEN TRAVERSE

0 minutes, 52 seconds Read
CHECK ON OPEN TRAVERSE
In open traverse, the measurements cannot be checked directly. But some field measurements can be taken to check the accuracy of the work. The methods are discussed below.
1. Taking cut-off lines Cut-off lines are taken between some intermediate stations of the open traverse. Suppose ABCDEF represents an open traverse. Let AD and DG be the cut-off lines. The lengths and magnetic bearings of the cut-off lines are measured accurately. After plotting the traverse, the distances and bearings are noted from the map. These distances and bearings should tally with the actual records from the field

2. Taking an auxiliary point Suppose ABCDEF is an open traverse. A permanent point P is selected on one side of it. The magnetic bearings of this point are taken from the traverse stations A,B,C,D, etc. If the survey is carried out accurately and so is the plotting, all the measured bearings of P when plotted should meet at the point P. The permanent point P is known as the ‘auxiliary point’

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *